Installation can be carried out by two workers, while fastening can be done by one worker using a standard tying tool or binding pliers.
After completing this stage, the cavity within the double panel is filled with concrete.
After placing reinforcement in the designated cavities of the floor panel according to structural calculations, concrete is poured over the panel.
The channels are created easily and quickly using hot air.
After creating the required openings, the welded mesh is removed where necessary using rebar cutters.
The finished walls are covered with cement mortar using a shotcrete machine before applying the final plaster layer.